What we do?
Main project objectives is Construction of surface Facility and necessary new drilling well for production of 65,000 oil and 78 MMscfd Gas in two stages, with maximum oil recovery from Sarvak formation.
The development plan will be implemented in two stages. In the first stage (Early Production Stage), it is planned to construct minimum surface facilities to produce 30,000 barrels of oil per day (BOPD). In the second stage (Final Production Stage), an incremental oil production of 35,000 bopd is planned to reach the final production rate that will be 65,000 BOPD. The facilities under construction in the two stages are:
Stage 1 (Early Production Stage):
- Drilling 7 producer wells.
- Work-over of existing well AZ-02 well and convert it to producer well.
- Drilling 1 appraisal well and completing it as a producer well (if possible).
- Drilling 1 delineation well and completing it as a producer or water disposal well.
- Construction of approximately 130 kilometers, 16 inch diameter, pipeline for transporting oil to Dehloran Production Unit.
- Construction of minimum surface facilities required for produced crude oil stabilization and separation of the associated sour gas.
Stage 2 (Full Production):
- Drilling 9 new producing wells.
- Construction of a production unit (Central Process Facility-CPF) with a capacity of 71,500 bopd and gas handling capacity of 78 MMscfd (billion standard cubic feet per day).
- Construction of 63 kilometers extension of the 16 inch oil transport pipeline from Dehloran to the junction of an existing main oil transport pipeline at Cheshmeh Khosh.
- Construction of approximately 130 kilometers, 16 inch diameter, pipeline for transporting sour gas to Dehloran.