The Project shall be implemented in two early and final production stages. The project consist of a main engineering, procurement and construction (EPC) including  all related activities for transportation of crude sour oil, crude sweet oil and sour gas from Central Process Facilities (CPF) to Dehloran and Cheshme Khosh production stations.

These activities include the construction of approximately 200 KM right of way (ROW), construction of 130 KM 16” sour oil pipeline, 130 KM 16” sour gas seamless pipeline and 63 KM 16” sweet oil pipeline, crossings include roads and rivers, Line Break Valve Stations (LBV’s), Pig Launchers and Receivers, Cathodic Protection Stations (CPS) and their electric supply lines, Fiber Optic Cable along the pipeline, Supervisory and Data Acquisition System (SCADA), Remote Terminal Unit (RTU), CCW & HTD.